SANTANA ROW
SAN JOSE, CALIFORNIA
Consolidated Engineering Laboratories (CEL) provided materials testing and inspection services on this
massive complex that consists of 680,000 square feet of retail; 1,200 luxury rental units that include
townhomes, lofts and apartment flats; a 214-room hotel; 5,200 parking spaces; and a 1,500 foot long
Mediterranean street. CEL's original scope of services included all materials testing and special
inspection services associated with post-tensioned concrete, structural steel, reinforced concrete, shear
wall diaphragm nailing and masonry.
CEL also performed inspection and testing services for the bulk of the tenant improvements
working for a large number of clients and with a multitude of general contractors.
Subsequently, and as a result of the Santana Row fire on August 20, 2002, CEL performed damage inspection and consulting
services of the post-tensioned slabs and structural steel members.
Client:
Federal Realty
Bruce Armiger – (408) 551-4603
Architect:
Merrit & Harris, Inc. – (818) 500-1174
Blacken Arrigoni & Ross Inc. – (415) 441-4771
Sandy & Babcock International – (415) 673-8990
Structural Engineer:
L.S. Mason & Associates
Bob Teal – (925) 283-8805
General Contractor:
Bovis Lend Lease
John Chiaverini – (408) 551-4675
Duration:
January 2001 – August 2005
Construction Costs:
$750 Million
CEL Fees:
$750 Thousand