click to open the Adobe Acrobat file

COALINGA STATE HOSPITAL
SECURE TREATMENT FACILITY
COALINGA, CALIFORNIA

Consolidated Engineering Laboratories (CEL) providedg materials testing and special inspection services on this massive 320-acre site development. This campus includes 48 one and twostory buildings that total over 1.2 million square feet. CEL also provided all off-site fabrication inspection services to seven facilities operating multiple shifts. The scope of services provided by CEL includes: reinforced concrete, post-tensioned concrete, masonry, structural steel and welding (shop and field), fireproofing and soils.

OF SPECIAL INTEREST:
  • CEL mobilized a full service laboratory that was completely operational and certified by the Department of General Services to the project site within one month's notice.
  • CEL had a staff with as many as 13 inspectors on site and 7 inspectors off site during the peak construction periods.
Client:
Department of General Services RESD Project Management Branch
Art Iwasa – (916) 376-1737
Architect:
Kaplan McLaughlin Diaz
Paul Busch – (559) 935-9094
General Contractor:
Hensel Phelps Construction Company
Jason Burke – (559) 934-1668
Duration:
July 2003 – July 2005
Construction Costs :
$400 Million
CEL Fees:
$2.3 Million