COMMUNITY HOSPITAL OF MONTEREY
MONTEREY, CALIFORNIA

Community Hospital of the Monterey Peninsula (CHOMP) project was a remodel and expansion of an existing facility. The new pavilions were cut into an existing slope, utilizing subterranean masonry construction and spread footing foundations. The structure, being structural steel, integrated with masonry and concrete walls. The exterior of the buildings was covered with GFRC panels. CEL performed structural steel and GFRC fabrications at off-site locations. On-site inspections included welding, masonry, concrete, and proofload testing. This project was issued 14 different OSHPD numbers for construction. CEL tracked each activity and reported separately to each number.
Client:
Community Hospital of Monterey
Fredrick Bensch – (831) 625-4766
Architect:
HDR Architecture, Inc.
Bill Naprstek – (626) 564-2820
Inspector of Record:
GAN Associates
George Naranic III – (408) 266-8914
Structural Engineer:
ZPFF Consulting Engineers
Mike Dygean – (310) 665-1536
General Contractor:
John F. Otto, Inc.
Dennis Buskirk – (831) 625-5015
Duration:
December 2003 –
Construction Costs :
$18.4 Million
CEL Fees:
$138 Thousand