click to open the Adobe Acrobat file

STANFORD UNIVERSITY
ARRILLAGA FAMILY SPORTS CENTER
STANFORD, CALIFORNIA

CEL worked closely with Vance Brown and the donor to provide a full scope of services consistent with the Stanford standard of care. Structural steel shop fabrication inspection was performed at Bambacigno Steel utilizing two shifts over two months. CEL performed intermittent quality control inspection of precast cladding and waterproofing.
Scopes of Service provided concrete placement, reinforcing steel, precast concrete, post tensioned concrete, shotcrete, shop and field welding, anchor dowel installation, epoxy injection and waterproofing testing and inspection.
Client:
Vance Brown
Rod Humble – (650) 849-9900
Construction Manager:
Consolidated Construction Management
Matt Scoble
(510) 208-1720
Architect:
Hoover & Associates
Lee Ashby – (650) 327-7400
Structural Engineer:
Middlebrook & Louie
Jason Louie – (415) 477-9000
General Contractor:
Vance Brown, Inc.
(650) 849-9900
Duration:
2004 - 2005
CEL Fees:
$77 Thousand