LIBERTY UNION HIGH SCHOOL
MODERNIZATION & UPGRADES
BRENTWOOD, CALIFORNIA

Consolidated Engineering Laboratories, as the prime consultant for materials testing and construction inspection, assisted the Liberty Union High School District, Construction Manager and Inspector of Record with their quality assurance program for the construction of Phases I and II, including all site work and new building structures. Our services for the project also included geotechnical engineering, grading observations and soils testing. Phase II (structures) along with soils testing responsibilities, includes concrete, masonry, structural steel and fireproofing.
Client:
Liberty Union High School District
Wayne Reeves
(925) 634-2166
Inspector of Record:
Greg Birtchet
(925) 584-5922
Structural Engineer:
William R. Dawson
Structural Engineer
(510) 549-3241
General Contractor:
Liberty Union High School District
Wayne Reeves
(925) 634-2166
Duration:
2003 - 2004
Construction Costs:
$23 Million
CEL Fees:
Approximately $50 Thousand